SUBJECT

 

Reference to

Paragraph

Page(s)

Preface

vii

Overview

 

ix – xii

CHAPTER- 1

OVERVIEW OF GOVERNMENT COMPANIES AND STATUTORY CORPORATIONS

1-18

Introduction                  

1.1

1

Working Public Sector Undertakings (PSUs)

1.2 –1.8

2-7

Working Government companies

1.9-1.10

7-8

Working Statutory corporations

1.11 – 1.14

8-9

Reforms in Power Sector

1.15– 1.16

9

Non-working PSUs

1.17 – 1.21

10-12

Status of placement of Separate Audit Reports of Statutory corporations in Legislature

1.22

13

Disinvestment, privatisation and restructuring of
Public Sector Undertakings

1.23 -1.24

13-14

Results of audit by Comptroller and Auditor General of India

1.25

14-16

Recoveries at the instance of audit

1.26

16

Internal audit/internal control

1.27

17

Recommendations for closure of PSUs

1.28

17-18

Position of discussion of Audit Reports (Commercial) by the Committee on Public Undertakings (COPU)

1.29

18

619-B Companies

1.30

18

     

 


SUBJECT

 

Reference to

Paragraph

Page(s)

CHAPTER – 2

REVIEWS RELATING TO GOVERNMENT COMPANIES

 

21-52

1.   Environmental safeguards in thermal power stations of Andhra Pradesh Power Generation Corporation Limited

 

21-38

Highlights

--

21

Introduction

2.1.1

22

Scope of audit

2.1.2

22

Audit objectives

2.1.3

22-23

Audit criteria

2.1.4

23

Audit methodology

2.1.5

23

Audit findings

2.1.6 – 2.1.32

23-37

Regulatory mechanism

2.1.7 – 2.1.9

24-25

Air pollution

2.1.10 to 2.1.21

25-32

Noise pollution

2.1.22

32-33

Water pollution

2.1.23 to 2.1.31

33-36

Other related issues

2.1.32

37

Conclusion

--

37-38

Recommendations

--

38

2.    Purchase and sale of electrical energy in Central Power Distribution Company of Andhra Pradesh Limited

 

39-52

Highlights

 

39

Introduction

2.2.1

39-40

Scope of audit

2.2.2

40

Audit objectives

2.2.3

40

Audit criteria

2.2.4

40-41

Audit methodology

2.2.5

41

Audit findings

2.2.6 – 2.2.25

41-52

Tariff mechanism

2.2.7

42

Purchase and sale of energy

2.2.8

42-43


SUBJECT

 

Reference to

Paragraph

Page(s)

Purchase of energy

2.2.9

43-44

Sale of energy

2.2.10 to 2.2.18

44-48

Remote metering cell

2.2.19

48-49

Undue favour to consumers

2.2.20

49

Incentive to ineligible consumers

2.2.21

49-50

Non-collection of additional consumption deposit

2.2.22

50

Misclassification of consumers

2.2.23

50-51

Drawals in excess of quota fixed for sub-stations

2.2.24

51

Audit of receivables

2.2.25

51-52

Conclusion

--

52

Recommendations

--

52

CHAPTER – 3

Transaction Audit Observations

3

55-85

Government Companies

 

55-74

Transmission Corporation of Andhra Pradesh Limited

 

 

Extra expenditure due to delay in finalisation of tenders

3.1

55-56

Extra expenditure due to opting for fresh tenders

3.2

56-57

Purchase of power from an independent power producer

3.3

57-60

Delay in finalisation of tenders

3.4

60-61

Southern Power Distribution Company of Andhra Pradesh Limited

 

 

Incorrect application of tariff

3.5

61-62

Eastern Power Distribution Company of Andhra Pradesh Limited

 

 

Incorrect recording of consumption

3.6

62-63

Andhra Pradesh Tourism Development Corporation Limited

 

 

Loss of revenue due to delay in determining land area offered for lease

3.7

63-65


SUBJECT

 

Reference to

Paragraph

Page(s)

Implementation of lake resort and eco-tourism projects

3.8

65-66

Non-collection of service tax

3.9

66-67

The Singareni Collieries Company Limited

 

 

Environmental aspects in coal mining

3.10

67-70

Andhra Pradesh Industrial Infrastructure Corporation Limited

 

 

Non-collection of value of land handed over to joint venture company

3.11

70-71

Andhra Pradesh State Civil Supplies Corporation Limited

 

 

Uneconomic transportation of foodgrains

3.12

72-73

Andhra Pradesh Industrial Development Corporation Limited

 

 

Doubtful recovery of term loan

3.13

73-74

Statutory corporations

 

74-82

Andhra Pradesh State Warehousing Corporation

 

 

Irregular payment of production incentive

3.14

74-75

Construction of godowns without commitment for occupation

3.15

75-76

Undue benefit to private investors

3.16

76-77

Loss of revenue

3.17

77-78

Andhra Pradesh State Road Transport Corporation

 

 

Avoidable payment of hire charges

3.18

78-80

Avoidable payment of interest

3.19

80-81

Purchase of piston assemblies and ring sets at extra expenditure

3.20

81-82

General

 

 

Follow up action on Audit Reports

3.21

82-85

 


 

' 

 


Annexure No.

SUBJECT

Reference to paragraph

Page(s)

Annexure 1

Statement showing particulars of up-to-date paid-up capital, budgetary outgo, loans given out of budget and loans outstanding as on
31 March 2005 in respect of Government companies and Statutory corporations

1.4,1.5,1.6, 1.17
 and 1.23

89-96

Annexure 2

Summarised financial results of Government companies and Statutory corporations for the latest year for which accounts were finalised

1.7,1.8,1.9,
1.10,
1.14,1.20,
1.21, 1.25 and 1.28

97-104

Annexure 3

Statement showing subsidy received, guarantees received, waiver of dues, loans on which moratorium allowed and loans converted into equity during the year and subsidy receivable and guarantees outstanding at the end of 31 March 2005

1.6

105-109

Annexure 4

Statement showing financial position of Statutory corporations

1.8

110-112

Annexure 5

Statement showing working results of Statutory corporations

1.8

113-115

Annexure 6

Statement showing operational performance of Statutory corporations

1.13

116-118

Annexure 7

Statement showing status of implementation of reform programme against each commitment made in the MOU

1.15

119

Annexure 8

Statement showing paid-up capital, investment and summarised working results of 619-B companies as per their latest finalised accounts

1.30

120

Annexure 9

Statement showing the installed capacity and date of commissioning of the thermal power plants of Andhra Pradesh Power Generation Corporation Limited

2.1.1

121

Annexure 10

Details of ESPs installed, designed SPM level, prescribed SPM level and actual SPM level recorded

2.1.11

122

Annexure 11

Year-wise position of quantity of sales allowed by APERC and actual quantity sold there against for the years 2001-02 to 2004-05

2.2.8

123


 

Annexure No.

SUBJECT

Reference to paragraph

Page(s)

Annexure 12

Details of energy sold to subsidised and non-subsidised category of consumers for the years 2001-02 to 2004-05

2.2.10 and 2.2.11

124

Annexure 13

Details of production as per consent order issued by APPCB vis-à-vis actual production area-wise

3.10

125

Annexure 14

Details of SPM levels in open cast (OC) mines as per base line data vis-à-vis actuals

3.10

126

Annexure 15

Statement showing paragraphs/reviews for which explanatory notes were not received (30 September 2005)

3.21.1

127

Annexure 16

Statement showing Department-wise break-up of outstanding Inspection Reports (IRs)

3.21.3

128

Annexure 17

Statement showing the department-wise draft paragraphs/reviews to which replies are awaited

3.21.3

129

 

GLOSSARY

130-132