GRANT No.XI ROADS, BUILDINGSAND PORTS (Contd.)
Head
Total grant
Actual
Excess(+)
expenditure
Saving(-)
(Rupees in lakh)
80 General
MH 001 Direction andAdministration
3.SH(03) DistrictOffices (Divisional
andSub-Divisional Offices)
O.
2,28,62.33
R.
(-)53,77.22
1,74,85.11
1,81,97.13
(+)7,12.02
Reduction in provision was the net effect of decrease of
`
53,89.28 lakh and an increase
of
`
12.06 lakh. Out of the total reduction in provision, decrease of
`
43,50.49 lakhwas stated
to be due to non-filling up of vacant posts. Specific reasons for remaining decrease of
`
10,38.79
lakh as well as increase in provision of
`
12.06 lakh have not been intimated.
Reasons for final excess have not been intimated (August 2013).
2216 Housing
05 General PoolAccommodation
MH 053 Maintenance and Repairs
4.SH(04) Construction
O.
58.75
R.
(-)51.19
7.56
7.56
Specific reasons for reduction in provision have not been intimated (August 2013).
5.SH(05) Maintenance and Repairs of
Buildings
O.
15,04.66
R.
(-)4,72.81
10,31.85
10,31.69
(-)0.16
Out of the total reduction in provision by
`
4,72.81 lakh, decrease of
`
2,04.09 lakh was
stated to be due to non-commencement of works for want of Administrative orders. Specific
reasons for remaining decrease of
`
2,68.72 lakh have not been intimated (August 2013).
3051 Ports and Light Houses
02 Minor Ports