GRANTNo.IIIADMINISTRATIONOF JUSTICE (Concld.)
Head
Total grant
Actual
Excess(+)
Expenditure
Saving (-)
(Rupees in lakh)
2059 PublicWorks
01 Office Buildings
MH 053 Maintenance and Repairs
10.SH(09) Buildings ofHighCourt
20,88.00
18,55.84
(-) 2,32.16
Reasons for final saving have not been intimated(August 2013).
Similar saving occurred during the years 2009-10 to 2011-12.
CAPITAL
(i) As the expenditure fell short of even the original provision, the supplementary provision
of
`
75,24.00 lakh obtained inMarch 2013 proved unnecessary and could have been restricted
to a token provision wherever necessary.
(ii) Out of the saving of
`
1,38,21.93 lakh, only
`
1,37,56.76 lakh was surrendered in
March 2013.
(iii) Saving in original plus supplementary provision occurredmainly under:
4059 Capital Outlay on
PublicWorks
60 Other Buildings
MH 051 Construction
SH.(05)
Construction of Court
Buildings
O.
88,00.00
S.
75,24.00
R. (-)1,37,56.76
25,67.24
25,02.07
(-)65.17
Reduction in provision was stated to be due to non-commencement of works for want of
administrative orders.